Things are heating up in the Pilbara

Things are heating up in the Pilbara
Construction progress update for lithium Mid-Stream Demonstration Project

The Calix electric calciner at PLS’ Pilgangoora Operation has successfully completed full heat cycles, confirming performance to design specification across power draw and heating range.

Commissioning of the lithium Mid-Stream Demonstration Plant is progressing to schedule, with first spodumene calcination and lithium phosphate production expected in the September quarter of 2026.

The plant was officially opened on 5 June 2026 by Western Australia Premier Hon. Roger Cook MLA and then ARENA Chair Justin Punch, marking an important step in the development of a potential new pathway for more sustainable lithium processing.

Under the terms of the Mid-Stream Project restructure executed on 20 April 2026, Calix has also received the second and final A$5.7m cash payment from PLS Group Limited.

Learn more about Calix’s solutions for value-added, lower-carbon lithium and other critical minerals here.

Contact us Calix Limited

We are on a mission to help solve some of the greatest global challenges.

Construction progress update for lithium Mid-Stream Demonstration Project

Subscribe

Subscribe to our newsletter

Subscribe to receive our latest updates, news and quarterly newsletter.